Drywall starts in the front of building!
Drywall started to be hung in the office spaces- really changing the look of the space! Exterior siding was hung around ½ of the building so far. The plumbing and HVAC continues to be installed in the front office spaces. So much happening at once!
Previous
Previous
Insulation is hung, siding continues
Next
Next